Approving a supplier qaimə and splitting it by cost centre
What you'll learn
- How to open a qaimə approval task
- How to split the qaimə's amount by cost centre and account
- The rules the split must follow before you can approve
- What happens after you approve or reject
Before you start
You don't need to be an accountant. The split is your estimate of how the goods or services on the qaimə are used: for example, that 700 AZN of a fuel qaimə went to deliveries and 500 AZN to the factory. The accountant later decides the final accounts, amounts and VAT.
Not every approval step asks for a split. If your task has no Split by cost centre part, just check the qaimə and approve or reject it as usual (see Approving a task).
Opening the task
- Open Document Flow → My Tasks and click the qaimə's task. Its name is the one your company chose, for example "Confirm the supplier qaimə".
- The Document part shows the qaimə's details. To see the qaimə itself, click View document: the document is named after the qaimə's number and has its file attached.
- Scroll to Task Fields. The split is under Split by cost centre.
Splitting the amount
The form opens with one row. Each row says how much of one qaimə line went where:
| Field | What to choose |
|---|---|
| Qaimə line | The line of the qaimə, with its amount. On a one-line qaimə it is already chosen. |
| Cost centre | Where the goods or services were used, for example "ADM — Administration". Cost centre (optional) means you may leave it empty: choose — No cost centre —. |
| Account | What it was used for. Once you choose a cost centre, only its accounts are offered. Where the form lets you choose the account first, its cost centre is filled in when the account has only one. |
| Amount | How much of the line, in AZN, VAT included. A row with a line and no amount is filled with what is left of that line; change it if needed. |
- Click Add row to put part of a line, or another line, somewhere else.
- Click the remove button at the end of a row to delete it.
- A list with many entries opens a search box: type part of the name or code. Accents and capital letters don't matter.
Under the rows, Allocated by line shows, for each line, its amount with and without VAT and how much you have allocated, and the same for the Whole qaimə: "all allocated", how much is "unallocated", or how much is "more than this line".
The rules
VAT Portal checks the split when you click Approve. If something is wrong, it shows Check the split rows before approving. and a message on the row.
- At least one row, and every row complete: a line, an account, a cost centre unless it is optional, and an amount.
- Amounts are positive, with a dot for decimals and at most 8 decimals, for example 1234.56.
- The same cost centre and account only once per line. A pair already used on the line is greyed out with Already on this line in row …: change the account, or put the whole amount in one row.
- All rows together may not be more than the qaimə's total, VAT included.
These are allowed:
- Leaving a line unallocated, in part or entirely.
- Going over one line's own amount. This is only a warning, because your estimate may move an amount from one line to another.
If VAT Portal refuses the approval after the checks, it shows the reason, and nothing is saved. A message that ends with Field: … names the field to correct. Correct it and click Approve again.
Approving or rejecting
- Approve: the task goes to the next approver, or the approval is finished. Your split is saved with the qaimə: a company with its own ERP takes it from there, and in a company with Finance it goes into the supplier invoice, where the accountant checks it.
- Reject: write why (at least 5 characters). The approval stops; the qaimə itself doesn't change in e-Taxes. The accountant reads your reason and decides what to do.
- Delegate, if the step allows it, when someone else should decide. See Delegating a task to someone else.
Common questions
The Cost centre list is empty.
Your company has no cost centres to offer yet. The message says where an administrator creates them: in Finance → Cost Centres, or in Taxes for a company with its own ERP. Ask your administrator.
The account I need isn't in the list.
Only the chosen cost centre's accounts are offered. Choose another cost centre, or, if the cost centre is optional, choose — No cost centre — to see all accounts.
Do I have to split the VAT?
No. Amounts include VAT, and the accountant decides how the VAT is treated.
The qaimə has several lines. Must I allocate all of them?
No. Allocate what you can estimate; a line may stay unallocated.
Can I change the split after approving?
No. After approval the split is shown as it was saved. Tell the accountant, who can change the accounts in the books.
There is no Split by cost centre part on my task.
Your step doesn't ask for one. Check the qaimə and approve or reject it.